Św. Michała
Photo report from the construction site.
See the details of the construction progress in the second stage of theŚw. Michała investment.
Photo report from the construction site.
The Świętego Michała development is currently under construction, and the works are progressing according to the planned schedule.
The excavation works for the building have been fully completed for sections A, B, and C.
The blinding concrete along with full insulation of the garage slab has also been completed. Currently, reinforced concrete works are being carried out on level -1, including the construction of walls and columns. In section C, a portion of the garage ceiling slab has already been completed.
The planned completion date of the construction is Q1 2027.
General Contractor: Democo Poland
We invite you to familiarize with the list of available apartments at: www.swietegomichala.pl
w. Michała Investment – Stage 1 is now in the final phase of construction
The Św. Michała Investment – Stage 1 is now in the final phase of construction. This is the last chance to live on Św. Michała Street in Poznań. The only available apartment has an area of 97 m² with a very attractive layout.
We invite you to schedule a viewing of the apartment.